Table 1.2 d: Work
package description
Work package number
|
0
|
Start date or starting event:
|
Month 1
|
||||||||
Work package title
|
Consortium Management
|
||||||||||
Activity Type
|
MGT
|
||||||||||
Participant number
|
1
|
2
|
3
|
4
|
5
|
6
|
7
|
|
|
||
Participant short name
|
|
|
|
|
|
|
|
|
|
||
Person-months per participant
|
|
|
|
|
|
|
|
|
|
||
Objectives
Secure
the effective and efficient operational and financial management of the
project
Facilitate
the project-internal communication to ensure integration of work packages and
project results
Assure
quality by securing internal consistency within the project, and by
monitoring the effectiveness and impact of the project in relation to its
goals
Establishment
of a project website
|
Description of work
Task 1: This work package will establish and
implement the operational and financial management structure of the project.
Internal communication structures and information flows will be established.
Project progress will be monitored and evaluated. Regular interactions of the
Project Steering Group and three meetings of the Consortium Assembly will be
organised back-to-back with the project-internal workshops and the final
conference. The meetings of the Consortium Assembly will be organised in
Task 2: A
project website will be established to provide public access to all material
produced by the project.
|
Deliverables
Establishment
and maintenance of a project website (month 4)
|